# Group the map into lanes

> Put the map into lanes, one for each team, sprint, epic, release or other field, to see which dependencies cross from one lane to another.

Section: Guides · Web page: https://visualbacklog.app/docs/guides/group-into-lanes

A dependency inside one team is routine. A dependency between two teams, or between
this sprint and the next, is where plans go wrong. **Group** puts the map into lanes so
those are the lines that cross from one lane to another.

[Screen recording: Opening Group in the toolbar, choosing Team, then Sprint: the map is redrawn in lanes each time](https://visualbacklog.app/landing/clips/group.mp4)

*The same space grouped by team, then by sprint.*

## Group the map

1. Click **Group** in the toolbar.
2. Choose what a lane stands for, for example **Team** or **Sprint**.

![The Group menu open in the toolbar, listing None, Sprint, Epic, Team, Assignee and Status with a line describing each](https://visualbacklog.app/docs/group-menu.webp)

*The Group menu. Scroll it for Release and Space.*

The map is redrawn in lanes, and the button shows your choice, for example
**Group: Sprint**.

![The Nova space grouped by release: a lane for Nova 2.0 beta, a lane for Nova 2.0 and a lane named No release](https://visualbacklog.app/docs/group-release.webp)

*Grouped by release. Work with no release has a lane of its own at the bottom.*

## Read the lanes

- Each lane has a heading with its name and how much of its work is done. A sprint’s
  heading also says whether it is closed, active or future; a release’s says whether it
  is released.
- Sprints and releases are in date order.
- Work that belongs to no lane, such as a story with no team, gets a lane of its own
  at the bottom.
- The cards and links are the same as before. A line that leaves one lane and enters
  another is a dependency between two teams, two sprints or two releases.

## Work with one lane

1. Point at a lane’s heading. Two icons appear.
2. Click **Show what waits on another lane** to pick out the work items in this lane
   that depend on work in another.
3. Click **Open in Jira search** to open the lane’s work items as a list in Jira.

## Go back to the ungrouped map

1. Click **Group** in the toolbar.
2. Choose **None**.

## Good to know

- Grouping is your own preference. It is not a step for **Back** and **Forward**, and
  it does not change what anyone else sees.
- Every option is listed in the [grouping reference](https://visualbacklog.app/docs/reference/grouping.md).