# Change which link types count as dependencies

> Choose the Jira link types that mean one work item has to be finished before another, for everyone in a space.

Section: Guides · Web page: https://visualbacklog.app/docs/guides/change-dependency-link-types

Visual Backlog treats some links as dependencies: links that mean one work item has to
be finished before another. They decide what a work item is waiting on, what Backlog
health reports, the waves of Dependencies mode, and which work is highlighted as a
blocker. Other link types are still drawn, but do not count.

Unless a space says otherwise, the dependency link type is Jira’s **Blocks**. Change it
if your team uses another, such as *depends on*.

## Change the link types

You need to be an administrator of the space.

1. At the right of the map, click the fourth icon, **Settings**.
2. Open **Dependency link types**.
3. Click the list and tick the link types that are dependencies for your space.

![The Settings panel open at the right of the map, with Dependency link types showing blocks / is blocked by](https://visualbacklog.app/docs/settings.webp)

*Dependency link types, in the Settings panel.*

The choice applies to everyone in the space. The note under the list says who it applies
to and who can change it.

## Go back to Blocks

1. Open **Dependency link types** in the **Settings** panel.
2. Click **Reset to Blocks**.